Ringhals 3 restart moves to 20 December for valve repair; Ringhals 4 now due back on 22 November

A clay power station with an orange domed roof stands in front of an oversized clock, with small clouds on either side.
AI illustration · WUA

Ringhals 3 is now due to restart on 20 December, after a leaking valve is repaired, according to Vattenfall. Ringhals 4’s planned restart has moved from 20 November to Sunday, 22 November, because the unit needs more time to start up after a prolonged shutdown, SVT Nyheter reported on 19 November.

The change for Ringhals 3 follows a delay announced on Wednesday. In a Vattenfall statement cited by SVT, Ringhals production manager Sven-Anders Andersson said the leak was found during one of the startup tests used to check that the reactor’s systems work correctly. The valve is inside the reactor containment and must be repaired before the unit can return to service.