Nacka challenges Saltsjöbanan cost increase as regional estimate reportedly rises over 400%

Author: WUA RadarPublished: Updated: Reviewed:

Nacka Municipality disputes Region Stockholm's higher estimate for restoring the Saltsjöbanan track bed after use during the Värmdövägen expansion. The agreement was based, according to Nacka, on roughly SEK 68.5–70 million. A 2025 regional estimate is said to be over 400% higher after reclassification from an encroachment case to an investment project.

What happened?

Nacka and Region Stockholm signed an implementation agreement in December 2022. In February 2023, the regional transport administration specified an estimate of SEK 68.5 million, which the municipality says was at the upper end of possible levels then. Work was to be performed by the administration's framework contractor and handled as an encroachment case.

In late 2024, the municipality was told the work would be reclassified as an investment project, adding management, client and risk costs according to the transport administration. Nacka says the region's 2025 estimate consequently exceeded the 2023 level by more than 400%.

Location

Nacka, Stockholms län

Impact and significance

The difference may have a major effect on municipal finances. Nacka's 2025 annual report contains a SEK 70 million provision for the agreement, in line with the original estimate. The municipality argues that the region's change of project form—not explicit acceptance of unlimited cost—created the new level.

This is Nacka Municipality's account and legal position in an ongoing cost dispute. The article does not contain Region Stockholm's full response or the exact new total, so the matter should not be presented as finally resolved.

Background

The track bed was used during expansion of Värmdövägen and is to be restored. The municipality has written to the regional transport committee and leadership several times. On 15 September 2025, representatives of M, C, S, KD, L and NL sought referral back. On 15 December, M, C, KD, L and NL repeated objections.

Nacka says it intends to fulfil the agreement, but on the assumptions and cost estimate on which it was based.

Latest update

The municipality says it will scrutinise costs allocated to Nacka and object to components it believes fall outside the original agreement. Further reporting needs the region's account, any negotiation or legal review, and a verified final allocation of costs.